Current projects
These are our current projects which we work at present time
Construction of kitchen and toilets
Project startet: 2010
Project status: building had been constructet and is awaiting finishings
Start with foundation in 2010 2012: construction startet
2013: Toilets, kitchen and dining are awaiting finishings
Building of 4 classroom blocks that are awaiting fininishings
Project startet: 2010
Project status: The 4 classrooms had been constructet and are awaiting 2nd and 3rd stages of electrification
Start with foundation in 2010 2011: walls for 4 classrooms are up
October 2012: 4 classrooms are awaiting finishings
November 2012: classrooms get ceiling, tiling, skimming and painting
official opening on the 4th of December 2012
Piggery project
Project startet: 2012
Project status: startet with 2 pigs